Syvänsalmenkatu, Lapintilankatu ja Hyljetie street plan

Streets and trafficEspoonlahti

Syvänsalmenkatu, Lapintilankatu and Hyljetie are existing streets. They were built according to the plans of the first construction phase, allowing for temporary passage for motorists. The passage is needed to enable the construction of Meritie. In the solution in accordance with the street plans, Syvänsalmenkatu and Lapintilankatu are dead-end streets. In accordance with the street plans, there will be on-street parking on Hyljetie, Lapintilankatu and Syvänsalmenkatu and pedestrian and bicycle traffic connections will be improved. The street plans were approved by the Technical Services Committee on 15 November 2017.

Location

Syvänsalmenkatu, Lapintilankatu and Hyljetie

Phase

Legally valid

A new combined pedestrian and bicycle path will be built on the southern side of Syvänsalmenkatu at chainage 135–210. A turning point will be built both in the middle and at the end of the street. On the western part of the street, pedestrian and bicycle traffic will be on the roadway or alternatively on the Lapinsarka walkway. On-street parking is being built on the southern side of the street.

A new combined pedestrian and bicycle path will be built on the southern side of Lapintilankatu at chainage 10–110. A turning point will be built both in the middle and at the end of the street. On the eastern part of the street, pedestrian and bicycle traffic will be on the roadway or alternatively on the Lapinsarka walkway. On-street parking is being built on the southern side of the street.

Two raised pedestrian crossings will be built on Hyljetie. On-street parking is being built on both the right and left sides of the roadway. A separated pedestrian and bicycle path will be built on the eastern side of the street. There will be street trees along the street.

 

Construction

The streets will be built in accordance with the street plans after the building construction projects have been completed, provided that Meritie has been built. In connection with the construction of Meritie, Syvänsalmenkatu will be raised to its final elevation. According to estimates, the improvement of the pedestrian and cycling routes on Syvänsalmenkatu will start in 2026 after the construction project on plot 31154-1 has been completed.
 

The Finnish-language newsletter "Have Your Say Now" tells you what projects you can currently influence and what is happening in your local area. It also provides you with information on upcoming info events for residents. The newsletter is delivered straight to your email inbox every two weeks. Subscribe by clicking the image!

Contact information

Johanna Salo

Project Manager+358 46 8773086Tekniikantie 15, Otaniemi

Finnoo area

Customer Service of the Urban Environment

+358 9 81625100