Project description

The contract includes widening the water area of the Svinö marina by carrying out dredging in the eastern entrance area of the marina. The dredging material will be placed in the Rövargrundet water spoil area of the City of Espoo. In addition, six private waterway spar buoys will be installed to mark the entrance of the marina and a deeper water area.

Basic information about the project

Implementation period: 2/2025 – 4/2025

Main contractor: Suomen Vesityö Oy

City developer’s representative: Osmo Tiililä