Stormwater measures in Westendinpuisto

Streets and trafficTapiola

The object of the contract is the construction of a water supply for the following sections of the street and park: Munkkiluodonkuja, Westendinpuisto, Hiiralankaari and Westendintie. The site is located in Westend, Espoo.

Project description

The contract includes the construction of a new stormwater pipeline between Munkkiluodonkuja and Hiiralankaari and the sea. District heating work will also be carried out in the contract, and the lighting of the area will be improved.

The contract includes things such as pile driving, pillar stabilization, construction of a pile slab, lighting and green work, painting work, dredging work and filling of structural layers.

The contract will cause noise nuisance, especially during blasting and pile driving work. The contract will restrict movement in the area.

Basic information about the project

Implementation period: 2/2025–11/2025

Main contractor: TerraWise Oy

City developer’s representative: Jonas Lindgren