Lankasuo excavation, stage 1A

BuildingEspoon keskus

Project description

The contract concerns the following works located in Kulmakorpi, Espoo.

Stage 1A excavation of the Lankasuo excavation area for future landfill operations. Some of the blasted rock can be crushed. The work includes mass excavation for a future landfill, soil removal, levelling excavation and earthworks in the base area, building construction site roads and implementing stockpiles.

Constructing a settlement basin and ditches in the Lankasuo spoiled soil disposal site.

Constructing an extension of the Kulmankorvi noise barrier. The area has a previously-constructed noise barrier that will be extended in the east.

Basic project information

Implementation time: 12/2025 – 6/2029

Main contractor: Peab Industri Oy

City developer’s representative: Tommi Verho