Espoonlahti Electric Center
Local detailed plansEspoonlahtiAn amendment to the detailed plan will facilitate the construction of a substation to serve the needs of the greater Espoonlahti area. At this stage, the area’s property boundaries will be reviewed. The planning will also ensure that there is space left for possible future additional lanes to Länsiväylä and noise protection along the highway, and that the flying squirrel’s canopy connection to other core areas is secured in the planning area parallel to Länsiväylä. The participation and assessment scheme and preparation material are available for public review 20.10 - 18.11.2025.
Plan name
Espoonlahden sähköasema
Area number
410801
Type of land use plan
Local detailed plan amendment
Phase
Preparation phase
Applicant
Private landowner
Current issues and news about the plan
- 21.10.2025: Let’s talk about planning the residents' evening provided an opportunity to discuss the plan with the planners. Read a news article about the atmosphere at the event.
Read more about the preparation and content of the plan on the project webpage in Finnish
You can find current information about the progress of a plan on the plan webpage in Finnish. For more information, you can contact the planners. You can participate in the planning process by submitting an opinion during the preparation stage or an objection during the proposal stage.
What are the preparation stage, public review and proposal stage?
You can read more about the process of detailed planning and resident participation on the page Detailed planning process in stages. Read more about participation in planning from the page Participation is part of city planning.